Rejected work may consume machining, inspection and handling capacity before its disposition. Rework creates additional operations, but only approved engineering and quality processes can establish whether recovery is acceptable.

Scrap is more than a piece of rejected stock
Distinguish scrap, rework, repair, concession and sorting. They have different traceability requirements and cost implications. A nonconforming component is not automatically unusable, and a visually acceptable correction is not necessarily authorized.
Build the right model

Set the costing boundary before comparing dispositions. Record accumulated production cost separately from the additional cash and capacity required to complete the order. For a replacement decision, compare only costs that change between the available options. The rejected-lot analysis below shows how to apply this distinction.
Costs beyond the rejected component
Retesting, expedited replacement and outside finishing can create additional expenses. Schedule displacement is a separate capacity issue: count lost contribution only if the displaced work cannot be recovered elsewhere. Do not add a full machine charge and lost contribution for the same capacity without checking what each figure includes.
Assumptions that cause costly mistakes

Track defect cause, operation of discovery, parts affected, disposition approval, recovery time and recurrence. Earlier detection often limits exposure, but the preventive fix must address the root cause.
How to introduce a more reliable workflow
Compare cost of prevention and verification with verified avoidable loss over a representative period, not one exceptional incident.
Costing scrap and approved rework
- Identify the rejected unit and its accumulated material and conversion cost.
- Separate confirmed scrap from a candidate for engineering-approved rework.
- Estimate extra operations and inspection without counting original costs twice.
- Record final disposition, recovery yield and corrective-action results.
What to measure after implementation
Separate the accounting cost of nonconforming work from future cash spending and capacity opportunity cost. For each incident, record rejected quantity, stage of discovery, consumed material, machining and inspection time, authorized rework plan, outside costs and production disruption. Distinguish scrap from repair, rework, sorting and use-as-is concessions because their engineering approval and financial treatment differ.
Illustrative rejected-lot analysis
Ten components contain $25 raw material each and have already consumed 12 minutes per part at an internal machine cost of $50/hour. Allocated material is $250 and machining consumption is 10 × 0.2 × $50 = $100. The $350 total is an estimate of resources consumed; it is not automatically the incremental cash needed to replace the parts. Replacement production, overtime and displaced orders must be evaluated separately, without counting already included costs again.
For corrective action, record where the defect originated, where it was discovered and which control should have detected it earlier. Compare recurrence and verified cost-of-poor-quality trends after the fix. Disposition and inspection evidence can be attached using the inspection report template.
Explore related Metrik MFG resources: CNC Cost Calculator, Machining Job Traveler Template, Inspection Report Template and Manufacturing Applications & Solutions.
Editorial note: Illustrations and numbers are explanatory, not industry benchmarks. Verify all engineering, commercial and accounting assumptions for the specific project.
Frequently Asked Questions
How do scrap and rework differ?
Scrap is nonconforming material that cannot be economically or appropriately recovered; rework restores conformance using approved instructions.
Why is scrap cost larger than raw material alone?
The rejected item may already contain machine time, tooling, handling, inspection and outside processing expense.
Can every defective part be reworked?
No. Rework must be technically feasible and approved under the relevant engineering, quality and customer requirements.